首页
外语
计算机
考研
公务员
职业资格
财经
工程
司法
医学
专升本
自考
实用职业技能
登录
外语
You will hear five different people talking about the issues involved in having new buildings constructed and advice about new c
You will hear five different people talking about the issues involved in having new buildings constructed and advice about new c
admin
2018-03-18
46
问题
You will hear five different people talking about the issues involved in having new buildings constructed and advice about new construction projects.
For each extract, there are two tasks. For Task One, decide what problem occurred with the construction project from the list A-H. For Task Two, choose what advice about new construction projects each speaker gives from the list A-H.
After you have listened once, replay the recording.
Task One - Problem with new construction project
For questions 13-17, match the extracts with the problem that occurred with the new construction project, listed A-H.
For each extract, choose the problem that occurred with the new construction project.
Write one letter (A-H) next to the number of the extract.
A A completion stage on the building was missed.
B Spending on installations exceeded projected figures.
C The managers’ offices were poorly located.
D Equipment was inadequately tested.
E Ineffective air-conditioning was installed.
F Insufficient parking space was provided for delivery vehicles.
G Plans failed to include access to the site.
H Contractors’ costs went over budget.
Speaker2______
Part Two. Questions 13 to 22.
You will hear five different people talking about the issues involved in having new buildings constructed.
For each extract there are two tasks. Look at Task One. For each question, 13 to 17, decide what problem occurred with the construction project, from the list A-H. Now look at Task Two. For each question, 18-22, choose what advice about new construction projects each speaker gives, from the list A-H.
After you have listened once, replay the recording.
You now have 30 seconds to read the two lists.
[pause]
Now listen, and do the two tasks.
[pause]
Speaker One
Man: We decided to open this new production facility on the outskirts of Madrid. I think we felt that the location was not too difficult to commute to, space not a problem, etc. The proposal was well within budget, so we didn’t spot the fact that the necessary link road wasn’t included in the developer’s original outline. The problem was fixed, but completing on time was very tight - we nearly missed the opening. I think with hindsight I’d say that once you’ve sorted out your contractors, it’s worth making a small internal group responsible for overseeing things so somebody is looking at the detail. And this pays off even if they have to put aside their own work for a while.
Speaker Two
Woman: Things never turn out as planned when you’re looking at building. Costs always overrun, so we thought we were very smart in keeping a tight rein on the contractors. This focus on the site meant the manager responsible for internal fixtures, etc was on his own and went way over budget. It’ll take us a while to recoup this and, as you can imagine, he’s not very happy at the moment. Still, it’s a lesson. I think I’d recommend that this is not handled internally and that, even for smaller parts of the contract, it’s worth getting a range of companies to put in a bid. They, and you, are then tied to the best deal and your staff are not tested beyond their abilities!
Speaker Three
Man: There are always technical problems when you’re building on a new site - we couldn’t even get onto the site in the first week because the access hadn’t been finished on time. But it’s the ongoing problems that prevent it being a success such as new equipment constantly breaking down or, as in our case, a faulty ventilation system, which now needs replacing. In future, I would make sure I’d checked out whoever was fitting it with their previous customers. I think it’s important to give them targets of certain standards you want them to fulfil throughout the process. Perhaps it’s also worth getting a fairly senior member of staff to check up on these contractors.
Speaker Four
Woman: I have to say that when we built the new site in the Aosta valley the route in was very steep and we thought parking would be an issue - it was a big facility with lots of staff. We didn’t foresee that worrying about that would mean that the construction work fell behind and the contractors didn’t meet one of their interim deadlines. Fortunately, we still managed to control the costs. But it’s a learning curve and if we did it again, I think we could look into what other options were possible. We were offered what looked like a good deal, and we took it without really considering all the possibilities that the consultants on the project had suggested.
Speaker Five
Man: When you’re expanding onto a new site, I think it’s important to make sure the schedule is realistic. We really rushed through the various completion stages and prided ourselves on reaching all our targets. But this meant certain things were overlooked and we suffered a series of problems in the first few months the facility was open. We sent very few managers to the site as there wasn’t much space for them and that meant there weren’t enough people around to arrange the necessary checks on the machinery that kept the whole site operational. Certainly, I would recommend that several different options are considered when you’re arranging after-sales contracts. Make it competitive and make sure you get one that includes regular checks.
选项
答案
B
解析
转载请注明原文地址:https://www.kaotiyun.com/show/m6Kd777K
本试题收录于:
BEC高级听力题库BEC商务英语分类
0
BEC高级听力
BEC商务英语
相关试题推荐
Whatistrueaboutthespeakers?
Whatarethespeakersmainlytalkingabout?
Whatarethespeakersmainlytalkingabout?
Whathappenedinthecompanylastnight?
Whomostlikelyisgivingthetalk?
WhatkindofbusinessisDombeyandSons?
Forabouthowlonghasthecompanybeeninbusiness?
随机试题
Ifnoone______thephoneathome,ringmeatwork.
适宜的人体每千克体重总摄氟量为
中国甲公司与英国乙公司签订了进口成套设备的合同,分四批运输。两批履约后乙公司得知甲公司履约能力出现严重问题,便决定中止第三批的发运。另第一批设备装机后试机时有零件飞出,伤及一名工人。依《联合国国际货物销售合同公约》,下列哪些选项是正确的?(
可转换公司债券的转换期由()
ABC会计师事务所承办了丁公司2005年度会计报表审计业务。2006年8月,T公司之股东U公司以T公司2005年度会计报表审计工作存在重大过失,导致其发生重大投资损失为由,向法院提起诉讼,要求ABC会计师事务所承担民事赔偿责任。要求:ABC
从不合格品率为0.04的一批产品中随机抽出600个,在前300个产品中发现不合格品12个,后300个产品中发现不合格品18个,理论上每随机抽出的600个产品中的平均不合格品数为()。
从教师与学生的关系看,新课程要求教师应该是学生学习的()。
领导在一次会议上严厉地批评了你,而实际上错误是由于另一位同事小王的失误造成的。对此你如何与领导沟通?
【2014年吉林省第58题】小明将一枚硬币连抛3次,观察向上的面是字面还是花面,请你帮他计算出有2次字面向上的概率是多少?
简述知觉的组织原则。
最新回复
(
0
)