首页
外语
计算机
考研
公务员
职业资格
财经
工程
司法
医学
专升本
自考
实用职业技能
登录
外语
You will hear five different people talking about the issues involved in having new buildings constructed and advice about new c
You will hear five different people talking about the issues involved in having new buildings constructed and advice about new c
admin
2018-03-18
91
问题
You will hear five different people talking about the issues involved in having new buildings constructed and advice about new construction projects.
For each extract, there are two tasks. For Task One, decide what problem occurred with the construction project from the list A-H. For Task Two, choose what advice about new construction projects each speaker gives from the list A-H.
After you have listened once, replay the recording.
Task One - Problem with new construction project
For questions 13-17, match the extracts with the problem that occurred with the new construction project, listed A-H.
For each extract, choose the problem that occurred with the new construction project.
Write one letter (A-H) next to the number of the extract.
A A completion stage on the building was missed.
B Spending on installations exceeded projected figures.
C The managers’ offices were poorly located.
D Equipment was inadequately tested.
E Ineffective air-conditioning was installed.
F Insufficient parking space was provided for delivery vehicles.
G Plans failed to include access to the site.
H Contractors’ costs went over budget.
Speaker4______
Part Two. Questions 13 to 22.
You will hear five different people talking about the issues involved in having new buildings constructed.
For each extract there are two tasks. Look at Task One. For each question, 13 to 17, decide what problem occurred with the construction project, from the list A-H. Now look at Task Two. For each question, 18-22, choose what advice about new construction projects each speaker gives, from the list A-H.
After you have listened once, replay the recording.
You now have 30 seconds to read the two lists.
[pause]
Now listen, and do the two tasks.
[pause]
Speaker One
Man: We decided to open this new production facility on the outskirts of Madrid. I think we felt that the location was not too difficult to commute to, space not a problem, etc. The proposal was well within budget, so we didn’t spot the fact that the necessary link road wasn’t included in the developer’s original outline. The problem was fixed, but completing on time was very tight - we nearly missed the opening. I think with hindsight I’d say that once you’ve sorted out your contractors, it’s worth making a small internal group responsible for overseeing things so somebody is looking at the detail. And this pays off even if they have to put aside their own work for a while.
Speaker Two
Woman: Things never turn out as planned when you’re looking at building. Costs always overrun, so we thought we were very smart in keeping a tight rein on the contractors. This focus on the site meant the manager responsible for internal fixtures, etc was on his own and went way over budget. It’ll take us a while to recoup this and, as you can imagine, he’s not very happy at the moment. Still, it’s a lesson. I think I’d recommend that this is not handled internally and that, even for smaller parts of the contract, it’s worth getting a range of companies to put in a bid. They, and you, are then tied to the best deal and your staff are not tested beyond their abilities!
Speaker Three
Man: There are always technical problems when you’re building on a new site - we couldn’t even get onto the site in the first week because the access hadn’t been finished on time. But it’s the ongoing problems that prevent it being a success such as new equipment constantly breaking down or, as in our case, a faulty ventilation system, which now needs replacing. In future, I would make sure I’d checked out whoever was fitting it with their previous customers. I think it’s important to give them targets of certain standards you want them to fulfil throughout the process. Perhaps it’s also worth getting a fairly senior member of staff to check up on these contractors.
Speaker Four
Woman: I have to say that when we built the new site in the Aosta valley the route in was very steep and we thought parking would be an issue - it was a big facility with lots of staff. We didn’t foresee that worrying about that would mean that the construction work fell behind and the contractors didn’t meet one of their interim deadlines. Fortunately, we still managed to control the costs. But it’s a learning curve and if we did it again, I think we could look into what other options were possible. We were offered what looked like a good deal, and we took it without really considering all the possibilities that the consultants on the project had suggested.
Speaker Five
Man: When you’re expanding onto a new site, I think it’s important to make sure the schedule is realistic. We really rushed through the various completion stages and prided ourselves on reaching all our targets. But this meant certain things were overlooked and we suffered a series of problems in the first few months the facility was open. We sent very few managers to the site as there wasn’t much space for them and that meant there weren’t enough people around to arrange the necessary checks on the machinery that kept the whole site operational. Certainly, I would recommend that several different options are considered when you’re arranging after-sales contracts. Make it competitive and make sure you get one that includes regular checks.
选项
答案
A
解析
转载请注明原文地址:https://www.kaotiyun.com/show/26Kd777K
本试题收录于:
BEC高级听力题库BEC商务英语分类
0
BEC高级听力
BEC商务英语
相关试题推荐
A、 B、 C、 D、 C图片中桥横跨在江面上,人们在船上划桨,由此可以联想到river,water,bridge,boat,people,oar,row等几个单词。(A)选项中的pickup是指接送。人们
Whoisthespeakerprobablyaddressing?
Whatisthespeakermainlytalkingabout?
Whomightthespeakerbe?
Whatarethespeakersmainlytalkingabout?
Whathappenedinthecompanylastnight?
Whataretheytalkingabout?
Whataretheytalkingabout?
Whomostlikelyisgivingthetalk?
A、 B、 C、 D、 DSomebusinesspeopleareseatedaroundatable,talkingaboutsomepapersordocuments.Choice
随机试题
信威SCDMA系统的手持终端的极化方式是()极化。
门冬胰岛素的结构是
规划衔接要遵循的原则包括()。
【例题4·简答题】甲、乙、丙三位出资人共同投资设立丁有限责任公司(以下简称丁公司)。甲、乙出资人按照出资协议的约定按期缴纳了出资额,丙出资人通过与银行串通编造虚假的银行进账单。虚构了出资。ABC会计师事务所的分支机构接受委托对拟设立的丁公司的注册资本进行审
斯腾伯格认为在认知性智力活动中起着最重要的核心作用,它解决问题时使用的策略的智力内部构成成分是()。
______(油漆成)red,thebuildingstandsoutamongtherestandlooksveryattractive.(paint)
无效民事行为是指已经成立,但因欠缺民事法律行为有效条件而不具有法律约束力的行为。以下属于无效民事行为的是()。
ThegrowingtradegapbetweentheUnitedStatesanditstradingpartnerswouldcontinuetowiden,duetothecontinuedrepercuss
Prior to the UML, there was no clear leading(111)language. Users had to choose from among many similar modeling languages with m
A、Helikeship-hopdancingverymuch.B、HehasbeenonTVtwice.C、Hedoesn’tminddancinginthepublic.D、Heonlymakesfriend
最新回复
(
0
)