(74)are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result 

admin2009-09-20  5

问题 (74)are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion; they may also exert influence over the project and its results.

选项 A、Controls
B、Baselines
C、Project stakeholders
D、Project managers

答案C

解析 项目干系人是积极参与到项目中,或其利益可能会受项目执行或完成结果影响的个人或组织:他们可能会对项目及其结果施加影响。