The customer asks your project to be completed 6 months earlier than planned.You think this target can be reached by overlapping

admin2017-09-14  3

问题 The customer asks your project to be completed 6 months earlier than planned.You think this target can be reached by overlapping project activities.This approach is known as ______.

选项 A、balance engineering
B、fast-tracking
C、1eveling
D、crashing

答案B

解析 本题考察项目进度管理知识。客户要求你的项目比计划提前6个月完成。你认为这个目标可以通过重叠的项目活动来达到。这种方法被称为快速跟进。